Regulatory Approvals

JUNG-ANG ENG can produce pressure vessels and heat exchangers based on the relevant domestic regulations.

Heat Using Equipment & Material

Manufacturing Inspection

Type Item Name Scope
Type Pressure Vessel Type 1 The value of maximum allowable working pressure (MPa) multiplied by internal volume (㎥) exceeds 0.004, and vessel falls under any of the following.
  • Equipment that heats a solid or liquid by receiving steam or other heat transfer media or by generating steam, where the pressure in the vessel exceeds atmospheric pressure.
  • A vessel that generates steam through a chemical reaction in the vessel, where the pressure in the vessel exceeds atmospheric pressure.
  • A vessel that heats a liquid or generates steam to separate the components of the liquid in the vessel, where the pressure in the vessel exceeds atmospheric pressure.
  • A vessel in which the temperature of the liquid exceeds its boiling point at atmospheric pressure.
Type 2 Maximum allowable working pressure of gas in the vessel exceeds 0.2MPa, and vessel falls under any of the following.
  • Internal volume is 0.04㎥ or more
  • Internal diameter of the shell is 200mm or more (more than 300mm for a steam header) and the length is 1,000mm or more.

Scope of pressure vessels: Enforcement Rule of the Energy Use Rationalization Act [Attached Table 1] / Equipment subject to inspection: Article 31-6 of the same Rule (Article 39 (1) and Article 39-2 (1) of the Act) [Attached Table 3-3]

Installation Inspection

Inspection to check installation status after installing machinery or equipment subject to manufacturing inspection

Subject to inspection Article 39 (2) of the Energy Use Rationalization Act

  • A person who intends to install, or to use by modification, machinery and
    equipment subject to inspection
  • A person who intends to use machinery and equipment subject to inspection
    by altering their place of installation
  • A person who intends to reuse machinery and equipment subject to inspection
    after suspending their use

Penalties Article 73 of the Energy Use Rationalization Act

Imprisonment with labor for up to one year or a fine of up to KRW 10 million

  • Any person who fails to undergo an inspection of machinery and equipment
    subject to inspection, in violation of Article 39 (1), (2) or (4)
  • Any person who uses machinery and equipment subject to inspection,
    in violation of Article 39 (5)
  • Any person who imports machinery and equipment subject to inspection,
    in violation of Article 39-2 (3)

Validity of an inspection
Article 31-8 (1) of the Enforcement Rule of the Energy Use Rationalization Act (the validity of an inspection)
[Attached Table 3-5]

Inspection types Validity of an inspection
Inspection types
Installation inspection 2 years
Remodeling inspection
Relocation inspection
Reuse inspection
Continued-use inspection Safety inspection
Validity of an inspection
2 years


Special validity periods Note 4 of [Attached Table 3-5] of the Enforcement Rule of the Energy Use Rationalization Act

  • Equipment at sites that prepare both a safety improvement plan and a process safety report : 4 years (extendable up to 8 years)
  • Equipment at sites that prepare either a safety improvement plan or a process safety report : 2 years (extendable up to 6 years)
  • Pressure vessels of GMP-compliant manufacturers of biological products : 4 years (extendable up to 8 years)

Inspection body Article 69 of the Energy Use Rationalization Act

  • Korea Energy Agency (KEA) (Competent ministry: Ministry of Climate, Energy and Environment)

* Standards for Inspection and Exemption of Heat-Using Equipment (Notice No. 2025-61, Ministry of Climate, Energy and Environment) / Energy Use Rationalization Act (effective 2026.5.28) and its Enforcement Rule (effective 2026.6.22)